Orleans County (New York) posted this IFB on Nov 5, 2026. Responses are due Dec 4, 2026. Category: Construction - Heavy & Civil. Solicitation number 2140359.
This bid was found on the agency's procurement portal. The portal's own text is not republished here; the summary below was written by ProposalWorkspace's AI from the bid documents. The full posting is on the portal - sign up free to get the link.
Summary fields on this page were extracted by AI from the bid documents. Always verify dates, amounts and requirements against the official solicitation.
This is a Orleans County sponsored, federally funded BridgeNY project.
Notice is hereby given, that sealed proposals are sought and requested for the purpose of entering into a contract with the Orleans County Department of Public Works, for the following:
Replacement of Gillette Road Bridge over Unnamed Creek
Town of Barre, Orleans County, New York
BIN 3319280, PIN 4BNY.79
The Project Owner is the Orleans County Department of Public Works, 225 West Academy Street, Albion, NY 14411.
This project, the replacement of Gillette Road bridge over Unnamed Creek, BIN 3319280, PIN 4BNY.79, will replace the existing Gillette Road bridge over Unnamed Creek in the Town of Barre, Orleans County. The project includes removal of the existing bridge, replacement with a 3-sided precast concrete structure and invert slab, highway approach work, and stream work.
Construction of this project will be done in strict accordance with the New York State Department of Transportation (NYSDOT) policies, procedures, and Standard Specifications (U.S. Customary Units), latest edition, and all addenda in effect on the date of advertisement for bids.
All bids must be submitted on the blank forms provided in accordance with the specifications.
On or after November 5, 2026, electronic copies of the Contract Documents may be obtained via email upon payment of **$25.00** (by non-refundable check, made payable to Orleans County Department of Public Works). Contract Documents will not be provided until the aforementioned $25.00 payment is received by the County. Only those who have purchased Contract Documents directly from Orleans County will be provided addenda and will be allowed to submit a bid.
The project duration is 76 days to substantial completion after notice to proceed. Project shall be substantially complete and open to traffic no later than November 12, 2027.
Bids shall be accompanied by a Bid Security of not less than five percent (5%) of the amount of the Bid. Such Bid Security shall be submitted in the form of a Bid Bond. [...] the required Performance and Payment Bond will be given [...].
All bidders will be required to sign a statement of non-collusion, which is included in the project bid package.
Questions regarding the Contract Plans and Documents for this project may be directed to Joel P. Astyk, P.E., Project Manager, Bergmann, at joel.astyk@collierseng.com. All questions shall be submitted in writing.