New York State Office for People with Developmental Disabilities (New York) posted this RFQ on Nov 3, 2026. Responses are due Nov 16, 2026. Category: Construction - Heavy & Civil. Solicitation number 2140502.
This bid was found on the agency's procurement portal. The portal's own text is not republished here; the summary below was written by ProposalWorkspace's AI from the bid documents. The full posting is on the portal - sign up free to get the link.
Summary fields on this page were extracted by AI from the bid documents. Always verify dates, amounts and requirements against the official solicitation.
OPWDD’s Broome DDSO is soliciting quotes for Repair or Replacement of Cathodic Protection on the Heating water system at our Valley Ridge CIT Located at: 276 County Road 46 Norwich NY.
The vendor shall provide all labor and materials necessary to complete the work in a professional manner according to this scope of work and architectural drawings if supplied.
Repair and replacement of sacrificial magnesium cathodic protection anodes that have exceeded their lifespan. The existing anodes protect pre-fabricated Perma-Pipe service pipes that extend from the main facility to each housing unit and return to the main facility. These anodes have been tested and determined to be inadequate for providing sufficient protection and require replacement.
Contractor shall warrantee work for a period of one year from date of payment for job. Warrantee shall be for parts and labor.
Work shall conform to all applicable codes, be done according to manufacturer’s instructions, and follow industry best practices.
Underground utility locations provided are approximate and must be verified in the field by the contractor. The contractor is responsible for locating utilities within the project corridor before starting construction. Any damage to underground utilities resulting from construction activities must be repaired at no extra cost to the owner.
A technician certified at CP-2 or higher is required to supervise the installation of cathodic protection and conduct acceptance testing of the installation to ensure the system performs properly.
Anodes should be installed:
Anodes must be positioned at equal intervals along the length of the conduit or containment. Anodes should be soaked in water before backfilling. Sand should not be used as backfill around the anodes.
A cathodic structure-to-electrolyte potential of at least -0.850 V or more negative must be tested and confirmed following the installation of all cathodic protection anodes. A minimum negative (cathodic) polarization voltage shift of 100 mV must be measured between the structure surface and a stable reference electrode in contact with the electrolyte.
The ground surface must be replaced to match its original form. Upon completion of Cathodic Protection Repair, before removal of equipment and scaffolding, contractor is to schedule a quality control and quality assurance inspection with the Maintenance Supervisor.
Bid price is to include all materials, labor, disposal of materials fees, third party inspections, and site clean-up.
**Submit** your quote using the Official Bid Form (attached) to brm.bids@opwdd.ny.gov no later than **5:00pm on 11/16/26**. Quote Amount MUST be valid for 90 days AFTER Bid Deadline.
A SITE VISIT is **MANDATORY**. You must sign into the site visit for your bid to be valid. Contractors must arrive to the site visit on time as late arrivals will be ineligible to submit quotes.
The BROOME DDSO intends to award the contract to the most responsible and responsive vendor that provides the lowest cost and meets the requirements detailed in the scope of work. Selection may also include such issues as past performance.
This is a NYS Public Works Project and **Prevailing Wages MUST be paid**. Contractors are required to provide proof of registration (as required by Labor Law Section 220-i) as a minimum qualification and that failure to provide proof of registration will disqualify a bidder.
The awarded vendor will also be required to submit certificates of Liability, Worker’s Compensation and Disability Insurance as well as completed Lobbying Law Forms, and a Signed Appendix A.
Contract Term: 60 days of Award. Work must be completed within 60 days of receiving the purchase order.